Updated timescales for week commencing 25 January 2021
We've updated our estimated timescales for our key Disabled Students' Allowances work streams and attached the information below.
Workstream area | Oldest date | Current turnaround time |
DSA1 Application Forms | 15th January 2021 | 6 days |
Needs Assessment Reports | 22nd January 2021 | 1 day |
Supplier Invoices | 18th January 2021 | 5 days |
Student Claims | 18th January 2021 | 5 days |
Emails (students) | 21st January 2021 | 2 days |
Emails (suppliers) | 21st January 2021 | 2 days |
Emails (HEIs) | 22nd January 2021 | 1 day |
Emails (NACs) | 22nd January 2021 | 1 day |
Updated timescales for week commencing 18 January 2021
We've updated our estimated timescales for our key Disabled Students' Allowances work streams and attached the information below.
Workstream area | Oldest date | Current turnaround time |
DSA1 Application Forms | 6th January 2021 | 8 days |
Needs Assessment Reports | 12th January 2021 | 4 days |
Supplier Invoices | 4th January 2021 | 10 days |
Student Claims | 6th January 2021 | 8 days |
Emails (students) | 12th January 2021 | 4 days |
Emails (suppliers) | 13th January 2021 | 3 days |
Emails (HEIs) | 12th January 2021 | 4 days |
Emails (NACs) | 12th January 2021 | 4 days |
Updated timescales for week commencing 11 January 2021
We've updated our estimated timescales for our key Disabled Students' Allowances work streams and attached the information below.
Workstream area | Oldest date | Current turnaround time |
DSA1 Application Forms | 18th December 2020 | 11 days |
Needs Assessment Reports | 22nd December 2020 | 9 days |
Supplier Invoices | 22nd December 2020 | 9 days |
Student Claims | 21st December 2020 | 10 days |
Emails (students) | 23rd December 2020 | 8 days |
Emails (suppliers) | 5th January 2021 | 4 days |
Emails (HEIs) | 6th January 2021 | 3 days |
Emails (NACs) | 24th December 2020 | 7 days |
Updated timescales for week commencing 04 January 2021
We've updated our estimated timescales for our key Disabled Students' Allowances work streams and attached the information below.
Workstream area | Oldest date | Current turnaround time |
DSA1 Application Forms | 14th December 2020 | 12 days |
Needs Assessment Reports | 14th December 2020 | 12 days |
Supplier Invoices | 14th December 2020 | 12 days |
Student Claims | 10th December 2020 | 14 days |
Emails (students) | 15th December 2020 | 11 days |
Emails (suppliers) | 18th December 2020 | 8 days |
Emails (HEIs) | 15th December 2020 | 11 days |
Emails (NACs) | 15th December 2020 | 11 days |